UK Power Networks G98 application

I am just starting to do my first G98 (G99?) application for a 5kW Sunsynk with battery, no solar. I am in SE England and come under UK Power Networks.


From their drop-down list there does not seem to be a 5kW Sunsynk stand alone showing as compliant, only when accompanied by SS battery. Is this correct?


As we will not be exporting any power at any time, does this mean I can apply for a G98 and put zero in the max export box? How do I prove it will be zero export?


Slightly confusing is under the battery heading they ask if it is single or three phase. Fairly sure mine is DC.


Any help appreciated.



ree



227 Views
steve.morris9
steve.morris9
Aug 20, 2023

Hi Paul sunsynk do have 3.6kw stickers. I asked for some for my 5kw inverters and they sent 3.6kw by mistake. When I question this they told me they don’t do for the 5kw, but I’ve just seen Jacekoeski post above and see that they do